Execution · Testing and commissioning

Testing, commissioning and commissioning: no equipment is energized without being tested

We plan, execute and document preoperative electrical tests, controlled energization and performance tests of transformers, panels and switchgear, MCC, medium voltage cables, protections, drives and generation systems. You receive the operating equipment and the dossier that proves it.

Low voltage, 4.16 kV and 34.5 kV Offshore platforms and industry Own or third-party equipment
The problem

The most expensive time to discover a fault is the first power-up

At the end of a work the pressure is to start. It is fair when tests are skipped, “factory” settings are accepted and it is delivered without evidence. These are the situations we see the most:

Undetected shipping or assembly damage

A team that passed the test at the factory can arrive with moisture, a blow or a phoja connection. Without proof in place, the damage appears when energizing.

Protections with generic settings

Relays and switches that come out with factory values ​​and not with those of the coordination study: false trips or, worse, protections that do not trip.

Several suppliers, no one integrates

The board from one, the transformer from another and the drive from a third. Everyone tests their equipment; no one tests the entire system working together.

Delivery without evidence

Without signed protocols or reference values, the warranty is complicated and the maintenance area starts without a baseline against which to compare.

How we execute it

A sequence with two release points

Commissioning is not a test at the end: it is a sequence that begins before the equipment arrives on site. Nothing is energized without the release of preoperative testing, and nothing is delivered without accepted performance testing.

VMS Energy Commissioning Sequence Seven stages: plan and protocols, testing, on-site reception and pre-operational testing with de-energized equipment; release point for energized energy; controlled energy and performance tests with energized equipment; point of acceptance; delivery to operation with +Station and training. DE-ENERGIZED EQUIPMENT ENERGIZED EQUIPMENT 1 Plan andprotocols Scope and criteria 2 TestificationFAT In factory 3 Receptionon-site After transport 4 Testspreoperative SAT, no voltage 5 Energizationcontrolled By stages 6 Tests ofperformance With real load 7 Delivery toOperation Dossier and personnel Liberationfor energize Acceptanceof the customer
General commissioning sequence. The scope of each stage is adjusted to the team and the contract; We can enter third-party equipment from the on-site reception.

Commissioning plan and protocols

We define what is tested, with what method, with what acceptance criteria and who testifies. It is remembered before the work, not during the start.

Test testing of tests, FAT

We attend factory acceptance tests of transformers, CCMs, disconnectors and drives to confirm that the equipment meets the data sheet before shipping.

Reception and inspection on site

Transport verification, data plate, visible damage and assembly and interconnection conditions before any electrical test.

Preoperative electrical testing (SAT)

With the equipment de-energized: insulation, transformation ratio, resistances, verification of control wiring, adjustments and tripping of protections, interlocks.

Release to energize

Controlled energization and commissioning

Energization in stages with programmed maneuvers, voltage verification, phase sequence and no-load behavior; configuration and startup of drives, generation and control.

Function and performance tests

Operation with real load: transfers, synchronization, control and communication loops with SCADA or DCS, and closing of pending (punch list) with the client.

Customer acceptance

The seventh stage, delivery to operation, is detailed in Deliverables. For the technical details of each test on transformers, consult our guides. FAT and SAT tests and Installation and commissioning of transformers.

What we test and put into service

From transformer to control loop

We test the equipment and, above all, the system: how the transformer operates with its board, its protections, its backup and its control.

Equipment or systemTypical tests and verifications
Power and distribution transformersInsulation resistance and polarization index, ohmic resistance of windings, transformation ratio (TTR), power factor, running and performance tests. Analysis of Dielectric oil when applying.Reference: IEC 60076, IEEE C57.12.91
Medium voltage cables and accessoriesInsulation resistance, VLF tests on primary and secondary circuits, hypot on terminals and relief cones, verification of splices and premolded elbows.Reference: IEEE 400.2
Blocks, switchgear and sectioners MV/bet, MCCPre-operational testing of bars and switches, operation of switches, interlocks and control wiring, automatic transfers, Profibus or Modbus communication. See Medium Voltage switchgear and MCC.Reference: IEC 61439, IEC 62271-200
Electrical protectionsVerification of adjustments against coordination study of protections and fire tests of relays and switches.
MV and LV frequency changersInstallation, interconnection, configuration, functional tests, commissioning and performance tests with the motor and the process. See frequency changers.
Generation, synchronization and governorsCommissioning of speed governors, synchronizers and load control, synchronization with the CFE network, import and export. See Turbogenerators.
UPS, batteries and backupPre-operational testing, commissioning and performance testing of UPS, chargers and battery banks, including transfer of critical loads.
Control, automation and communicationsInterconnection and pre-operational testing of PLC, DCS and SCADA; verification of process and communication signals (Profibus, Profinet, Modbus).
Grounding systemsMeasurement of resistance of the ground network and continuity of equipment connections.

The standards cited are for reference; The protocol for each project is defined with the client, the project specification, the current NOM-001-SEDE and the recommendations of each manufacturer.

What you receive

A team operating and evidence that was tested

The commissioning dossier is the baseline for your maintenance: the values ​​against which each future test will be compared.

  • Plan and protocolsScope, method and acceptance criteria of each test, agreed before starting.
  • Test recordsMeasured values, test conditions and result of each team, signed by the witness.
  • Applied settingsFinal adjustments of protections, drives and control, as left on site.
  • To-do listPunch list with those responsible and documented closure of each observation.
  • Delivery dossierIntegrated commissioning file for operation, maintenance and guarantees.
  • Transfer to staffExplanation of the operation and maintenance of your equipment. See Training.
Documented experience

Commissioning on marine platforms, generation and industry

An important part of our projects includes pre-operational testing, commissioning and performance testing, from platforms in Campeche Probe to ingenuity and mines. Examples include:

34.5 kV
actuators and transformers put into operation
7.5MVA
transformer with FAT, installation and performance tests
1000 HP
mid-voltage units launched
Offshore
testing and commissioning on marine platforms

Pemex · Maloob A Platform

Campeche probe

Pre-operational electrical testing, commissioning and performance testing of Metal Enclosed distribution boards and motor control center.

Pemex · EK-A Platform

Campeche probe

FAT tests, installation, function tests, commissioning and performance tests of 7.5 MVA transformer and 34.5 kV nine-way disconnector.

Pemex · Balam-A Platform

Campeche probe

Primary electrical tests on 12 transformers (6 phase shifters and 6 boosters) and 34.5 kV distribution transformers.

CFE Central Chankanaab

Cozumel, Quintana Roo

Engineering, supply, installation and commissioning of AC and DC motor control centers.

SLB

Tabasco

Engineering, supply, installation and commissioning of two 1000 HP medium voltage drives and 4.16 kV distribution boards.

Baker Hughes

Campeche

Supply, installation and commissioning of 14 cabinet frequency variable frequency drives for intemperie.

Ingenio San Nicolás

Veracruz

Commissioning of the distribution board of the new power plant, with synchronization with CFE, import and export.

Infrastructure · Road tunnel

State of Mexico · 2025

Integration and commissioning of 12 cabinets with frequency converters and Profinet control via SCADA for ventilation and extraction.

See project catalogue → Caso CFE Chankanaab →
How to hire us

Within our EPC or as a commissioner of your project

Commissioning can be a stage of our project or a stand-alone service for equipment you have already purchased or installed by another contractor.

As part of an EPC project

When VMS designs, supplies and installs, commissioning is planned from engineering and closes with a single person responsible for the entire system.

For third-party teams or contractors

We test and commission equipment that others supplied or installed, of any brand, and integrate those from various suppliers into a single working system.

After a retrofit, expansion or failure

Testing and re-energization after a Retrofit, an increase in capacity or a repair, to return to operation with evidence and not by trial and error.

For whom

Operations where a failed start is costly

Where the start-up window is short and a delay or failure in first energization is measured in lost production.

Oil & Gas

Offshore platforms and land-based facilities, with short work windows and complex logistics. See solutions oil & gas.

Generation and cogeneration

Mills, paper mills and power plants with turbogenerators, synchronization with CFE and generation control.

Mining, manufacturing and infrastructure

Substations, MCC, pumping with variable frequency drives and ventilation systems where every day of delay in starting stops production. Mining.

Frequently asked questions

What difference is there between testing, commissioning and commissioning?
The tests verify the status of each piece of equipment, generally de-energized. Commissioning is the complete sequence that confirms that the system was installed and operates as designed, from test plan to performance testing. Commissioning is the energization and delivery to operation at the end of that sequence.
Can you commission equipment that you didn't supply or install?
Yes. We work in a multi-brand way and have put into service equipment from different manufacturers, supplied by third parties. In those cases we start with the reception and on-site inspection and define the protocol with the customer and the manufacturer's information.
Do you test factory tests for the FAT test?
Yes. We have participated in testing of transformers, engine control centers, 34.5 kV sectioners and frequency changers before your dispatch, as part of the supply or representing the customer.
What if a test does not meet the acceptance criteria?
The equipment is not released to energize. The result is documented, the cause is investigated with the manufacturer or installer, corrected, and the test is repeated. That's the reason for release points: to prevent a fault from being discovered upon energizing.
What do they deliver after the commission is over?
A T-shirt with plan and protocols, records of each test, settings applied in protections, variable frequency drives and control, the closed pending list and transfer to operation and maintenance personnel.
Do they work on offshore platforms and outside Jalisco and Campeche?
Yes. Much of our experience in testing and commissioning is on marine platforms of Campeche Probe, and we serve projects throughout Mexico, such as Tabasco, Veracruz, TON, Durango and the State of Mexico.