On-site generation

Cogeneration and on-site generation for industry

Control, synchronization, protection and grid interconnection for turbine-generators, engines and turbines operating in parallel with the grid. Multi-brand integration with a single point of accountability.

Mills in Mexico and Central America Synchronization with CFE Offshore generation platforms
Where we work

Three scenarios of own generation

On-site generation is not a single product. Fuel, thermal demand and relationship with the grid change control and interconnection engineering.

ScenarioTypical inThe criticalOur scope
Steam cycle cogenerationSugar mills (bagasse), paper mills, geothermalSpeed and extraction control, availability in harvest, export of surplusesGovernors, excitation, synchronization switchgear, protections and modernization of controls
Gas or diesel engines and turbinesOil & Gas platforms and process centers, remote sites, continuous process plantsLoad sharing between machines, ballast shedding, generator protectionElectrical and control integration with the engine or turbine manufacturer; generator maintenance
Generation in parallel with the gridIndustry with self-consumption or interconnected cogenerationControlled import and export, Network Code compliance, permitsSynchronization blockers, interconnection protection schemes and technical documentation for formalities

On natural gas cogeneration: we participate in electrical engineering, control, synchrony, interconnection and Balance of System, integrated with the engine or turbine supplier. The heat recovery equipment is defined by the project's thermal specialist.

What we do

From governor to interconnection point

Speed and load control

Supply, programming and commissioning of electronic governors; Thread of mechanical governors retaining actuators when technically feasible.

Excitation and voltage regulation

Automatic digital voltage regulators for voltage control, power factor and distribution of reagents in parallel with the network or in an island.

Synchronisation and burden sharing

Synchronization switchgear and boards, machine-machine and machine-network synchronization, import and export control.

Generator protection and studies

Generator protection relays, overspeed protection, short circuit studies, protection coordination and generation system load flows.

Interconnection and compliance

Interconnection engineering, protection schemes and technical documentation for procedures before CFE and the National Energy Commission.

Maintenance of generators and turbines

Specialized maintenance of synchronous generators, rehabilitation of auxiliary systems and mechanical service to turbines, with electrical tests and condition reports.

Control platforms that we integrate: Woodward, Basler Electric and DEIF, among others. Technical detail in Turbogenerator control.

Regulatory and fiscal framework

What you should know before generating your own energy

Permits (Electric Sector Law, 2025)

  • Plants less than 0.7 MW: distributed generation with interconnection contract, without permission from the CNE.
  • Self-consumption of 0.7 MW or more: requires generation permit from the National Energy Commission.
  • Between 0.7 and 20 MW in interconnected self-consumption, a simplified procedure applies.
  • Any interconnection must comply with the Network Code in protections, energy quality and control.

Tax incentive

The Income Tax Law (ISR, Article 34, Section XIII) allows a 100% deduction for machinery and equipment used to generate power from renewable sources, including biomass such as bagasse, or through efficient power cogeneration systems, provided the equipment operates for at least five years.

The qualification as efficient cogeneration and the application of the deduction must be validated with the regulator and with your tax advisor.

Reference projects

Generation that we already synchronized, protected and launched

Ingenio Adolfo López Mateos

Oaxaca

Engineering, supply and commissioning of the cogeneration system synchronization switchgear, with Woodward MSLC synchronizers and DECS-250 voltage regulation on the control panel.

Ingenio San Nicolás (via Eurocontrol Electric)

Veracruz

Consulting, supply and commissioning of the load distribution panel of the new power plant, with synchronization with CFE, import and export.

Santa Ana Sugar Mill

Escuintla, Guatemala

Engineering, installation and commissioning of synchronization and load distribution equipment for four turbogenerators, with vibration monitoring system.

Dragon Group — geothermal plant

Nayarit

New generation control system with synchronization with CFE, import and export, overspeed protection, excitation and vibration monitoring.

PG-ZAAP-C — Pemex

Campeche (offshore)

Installation of the 41.2 MW TG-704 turbogenerator on the generation platform, repair of the generator and rehabilitation of its cooler.

P.S.S. Chemul

Campeche probe

Supply, installation, configuration and start-up of load sharing control for a generation system with five Wärtsilä engines of 3,000 kW.

Lufussa — Pavana

Honduras

Modernization of the excitation system with DECS-250 for the Wärtsilä motor generator.

Ultra Papers

State of Mexico

Power plant: repair of two mechanical governors and commissioning of the 5 MW TG1 turbogenerator.

Akal-J3 — Pemex

Campeche (offshore)

Adaptation, installation and connection of control and measurement signals of the protection relays of the TG-01 and TG-02 turbogenerators.

How we work

Planned interventions around your operation

1. Diagnosis

Survey of the generation system, download of existing configurations, trip history and protection status.

2. Engineering

Control philosophy, single-wire lines, short-circuit and coordination studies, and multi-brand equipment specification.

3. Window execution

Planned assembly and connection for scheduled shutdowns or off-season, with preoperative tests before energizing.

4. Testing and transfer

Overspeed, charge rejection and timing tests; delivery of parameters, oscillograms and training to operating personnel.

Frequently asked questions

Do you run turnkey cogeneration projects?
Our proven experience is in the electrical and control part of generation: synchronization, excitation, governors, protections, interconnection and start-up. In new cogeneration projects we work together with the engine or turbine supplier and the thermal specialist, and we assume the electrical and control scope under a single contract.
Can you modernize the control of a Turbogenerator without changing the turbine?
Yes. It is one of our most frequent works in ingenuity: replacing obsolete mechanical or electronic governors with digital controllers, retaining actuators when technically feasible, and adding synchronization and communication with the plant control system.
What is needed to export surplus to the network?
A synchronization and interconnection protection scheme that complies with the Network Code, the corresponding contract or permit according to capacity (the threshold of 0.7 MW defines whether permission is required from the CNE) and the corresponding measurement. The economic viability of the export depends on the current rules of consideration.
Do they serve plants outside Mexico?
Yes. We have performed synchronization, excitement and control work in ingenuity and generation plants in Guatemala, El Salvador and Honduras.

Is your own generation ready for the next harvest or the next strike?

We review control, synchronization and protections of your generation plant and provide you with a prioritized intervention plan.

Request evaluation