Electrical Engineering for Sugar Mills and Agribusiness
Woodward turbine-generators, MV/HV substations, process automation and predictive maintenance for sugar mills in Mexico, during both the harvest and maintenance seasons.
The electrical pressure that every director of a sugar mill faces
The sugar industry operates under conditions that have no equivalent in other sectors: rigid seasonality, short maintenance windows and a cost of unemployment during the harvest that can exceed $500,000 MXN per hour.
Electrical seasonality without margin of error
During the harvest (November–May), the power plant operates at 100% capacity, 24 hours a day, for six continuous months. A failure in the turbogenerator, substation or Woodward governor can cost between $50,000 and $500,000 MXN per hour of lost production. There is no second chance: the cut cane deteriorates in hours and the grinding schedule cannot be recovered.
Massive starts in pre-harvest
At the beginning of the season, the mill starts dozens of high-torque motors—mills, diffusers, steam pumps, evaporators—in a few hours. Poor coordination of protections, a poorly configured drive or a faulty synchronization switchgear can generate chain trips that stop the entire factory right on start-up day. The pre-harvest is the time of greatest electrical risk of the year.
Short window for projects and investment
Repair (May–October) is the only window to execute important electrical projects: substation rehabilitation, updating of governors, installation of new CCMs or cables. If imported materials are delayed or engineering is not ready, the harvest starts with substandard equipment — and the next repair cycle is six months away.
Electrical services for sugar mills
The sugar industry has critical electrical requirements: own generation with turbosteam, interconnection substations with CFE and intensive maintenance during repair. VMS Energy covers the entire spectrum.
Steam Turbogenerators — Woodward
Programming and commissioning of Woodward 505, 505-XT and 2301D governors for counterpressure and extraction-condensation turbines. PID loop adjustment, overspeed test and synchronization with CFE network. Experience in more than 12 mills throughout Mexico.
MV/HV power substations
Design, construction and rehabilitation of 13.8–69 kV substations for sugar mills. Acceptance tests (TTR, VLF, contact resistance), synchronization switchgear for parallelism with CFE and major maintenance of transformers and switches.
Power plant automation
SCADA integration of the mill's power plant: monitoring of generation, distribution and consumption. Automation of process equipment: mills, diffusers, evaporators and centrifuges. Updating obsolete boards to modern PLCs with industrial Ethernet communication.
Predictive maintenance in repair
Electrical Thermography of Boards, MCC and Substation. Transformer Diagnostics (TTR, megger, DGA) during the annual repair stop. VLF test on MV cables to evaluate insulation status before the next harvest.
MCC and force distribution
Supply and installation of IEC 61439 Motor Control Centers (MCC) for factory, batey and cogeneration areas. Updating of mechanical starters to frequency variable frequency drives for energy saving in pumps and fans.
Power factor correction
Study of measurement, design and installation of APFC banks to correct the power factor before CFE and avoid penalties. Mills with high motor and furnace loads can reach FPs of 0.75–0.82, generating significant additional charges.
Electric cycle of the sugar mill
The sugar industry operates in defined annual cycles. VMS Energy accompanies the mill at each stage with the appropriate electrical services to maximize availability during the harvest.
Repair (May–Oct)
Major maintenance of turbines, governors and substation. Thermography, VLF, transformer diagnosis. Updating boards and MCC. Ideal time for EPC projects.
Pre-harvest (Oct–Nov)
Commissioning of Woodward turbogenerators and governors. Switch and switchgear testing. Adjustment of electrical protections. SCADA verification and control systems.
Zafra (Nov-May)
Emergency technical support, 2007. Response in less than 24 hours to failures in governors or electrical systems. Unscheduled stoppage costs between 50,000 and 500,000 BDN per hour.
Closing of the harvest (Apr–May)
Analysis of electrical performance of the harvest. Identification of improvements for the next season. Investment planning and repair projects.
Our history in the sugar industry
Presence in sugar mills in the main sugar producing states of Mexico: Veracruz, Morelos, Oaxaca, Jalisco, Michoacán, Tabasco, Campeche and San Luis Potosí.
Ingenio San Nicolás
Veracruz
Advice, supply and commissioning of the electrical load distribution panel of the new plant, including synchronization with CFE with import and export.
Ingenuity Emiliano Zapata
Morelos
Commissioning of a 2301D-ST governor with Valtek 50 actuator in turbogenerator 1, and subsequent modernization of the speed control with Woodward 505 electronic governor.
Ingenio Adolfo López Mateos
Oaxaca
Change of the 2301D-ST for a Woodward 505 Enhanced governor in turbogenerator 1, and start-up of the cogeneration system synchronization switchgear with MSCL II and DECS 250 on the control panel.
Santa Rosalía Sugar Mill
Tabasco
Commissioning of a Woodward 505 governor on turbogenerator 2, with supply and installation of a Valtek 50 actuator.
Santa Clara Sugar Mill
Michoacan
Supply, installation and commissioning of a Governor Woodward 505 at the NEB TG1 Turbogenerator, with adaptation of a new UG40 actuator; then modernization of turbine speed control and generation plant.
Three Valleys Mill
Veracruz
Increase in operational capacity in electrical substations no. 2 and no. 5, the latter in 4 160 V, and modification of the Electrobús BUS "C", all with electrical tests.
Tamazula Sugar Mill
Jalisco
Mechanical turbine service with dynamic balancing and blade and arrow testing; maintenance, installation and commissioning of speed governors; and a regenerative variator of 300 HP from Schneider Electric.
Ingenio Casasano
Morelos
Modernization of speed control for steam turbine with Peak 150 and Woodward PG-PL actuator.
Ingenuity of Autlán
Jalisco
Manufacture of bases for the speed governor, maintenance and commissioning.
Ingenio La Joya
Campeche
Supply, calibration and commissioning of Woodward's 2301 and 505 electronic speed governors, and supply of the Basler Electric DECS 250 excitation system.
Ingenuity The Bee
Morelos
Modernization of the speed control of a mill turbine with Peak 150.
Ayala Plan Ingenuity
San Luis Potosi
Commissioning of a 2301D-ST governor with CPC-1 actuator in turbogenerator 3.
Ingenio José María Morelos
Jalisco
Service tuning the automatic voltage regulator DECS from Basler Electric.
Advantages of working with VMS in the sugar sector
We understand the pressures of ingenuity: the harvest does not wait, unscheduled stoppages are devastating and engineering must be precise from the first attempt.
Response within 24 hours
During the harvest, we have an engineer available to travel to any point in the republic in less than 24 hours. Every hour of unemployment costs.
In-depth knowledge of the process
We understand the relationship between process steam generation and electricity generation. Our engineers have worked in more than 12 different mills.
EPC comprehensive service
From substation design to governor commissioning, we offer a single point of contact for all mill electrical engineering.
What the technical directors of sugar mills ask
Are you planning electrical projects for the next repair?
The best time to plan is now. Contact us for an evaluation of your electrical plant and a quote for repair services and the next harvest.
Request plant evaluation